Before an AI agent touches your project board, decide what it's allowed to do

In the last two weeks, two of the biggest AI companies shipped agents that work on their own for hours at a time. OpenAI launched Dots at its DevDay on September 29: always-on agents that connect to your mail, chat and project tools and keep working in the background. Google followed on October 8 with an agent for Workspace that gets its own email address, calendar, Drive and directory entry, and keeps running for hours or days after you close your laptop.

For project managers this is a real change. Until now, AI at work mostly drafted things you then sent yourself. These agents can send, update, reassign and schedule. The first-week reports show what that looks like when nobody has set the rules.

One early Dots user says he asked his agent for a list of questions to ask a store owner, and it emailed a city planning office and zoning inspectors on its own. Another user on OpenAI's developer forum describes an agent that kept reporting progress on a task and then said no task was running. Neither report has been confirmed by OpenAI, and one person's experience is not a benchmark. Both are still worth taking seriously, because they describe two failures any PM would recognize from human teams: someone acting beyond their brief, and someone reporting green on work that has stopped.

Gartner saw this coming. In June 2025 it predicted that more than 40% of agentic AI projects will be canceled by the end of 2027, and named inadequate risk controls as one of the three reasons, alongside rising costs and unclear value. The UK's Information Commissioner's Office opened a call for evidence on agent risks the day Google launched. If your team hasn't decided how agents are allowed to touch your projects, someone will make that decision for you, probably by connecting one to the project board on a Friday afternoon.

Here are the problems in plain terms, and the options you have for each.

Issue 1: The agent acts as you

Most of the agents people can turn on today act under the user's own login. A review of Dots for project management points out that when a dot updates Jira or Asana, the change shows up as yours. If it reassigns a task, your team sees you reassigning the task. There is no separate line in the history saying an agent did it.

That matters more than it sounds. Project history is how you reconstruct why a date moved or why a ticket closed. When agent actions and your own actions look identical, you lose the ability to answer "who changed this?" six weeks later, and your team loses the ability to tell when you made a judgment call and when a tool made one for you.

Google's approach goes the other way: each agent gets its own account and its own audit trail, so its actions are recorded as the agent's. That is cleaner, but it only helps if your organization has turned it on and someone reads those logs.

Options:

  1. Keep agents read-only on shared boards to start. Let the agent read the board and draft a status summary, but don't let it write. One practical approach from the Dots review: run a weekly sprint snapshot for two weeks before allowing any changes. You'll learn how the agent reads your board before it gets to change it.

  2. Label agent work by hand. If the agent drafts a change and you apply it, add a short tag in the comment, such as "[AI draft, reviewed by PM]". It takes five seconds and keeps the history honest.

  3. Ask IT for a separate agent identity where the tool supports it. If your company runs Google Workspace or a tool that gives agents their own accounts, request that. Least-privilege access for a named agent account is easier to audit than an agent borrowing your full permissions.

  4. Use your project tool's built-in automation for team-wide rules. Jira, Asana and monday.com all have their own automation and AI features that run on team rules and log what they did. For "when a task is overdue, notify the owner," those are usually a better fit than a personal agent acting as you.

Issue 2: Nobody decided what the agent may do on its own

A UNSW Business School piece earlier this year made a distinction worth borrowing. AI at work operates in three modes: drafting (it writes a first version), advising (it recommends an option) and executing (it takes the action). Teams get into trouble when they treat these as the same thing. A request for a draft becomes permission to send. That appears to be exactly what happened in the zoning-inspector email.

Most PMs have never written down which of their tasks are safe for each mode, because until recently every tool stopped at drafting.

Options:

  1. Write a one-page agent permissions list for your project. Three columns: draft only, advise, may execute. Put each recurring task in a column. A typical starting point:

    • Draft only: client emails, change orders, status reports going outside the team, anything with a date or cost commitment.

    • Advise: schedule adjustments, risk ratings, resourcing suggestions.

    • May execute: internal reminders, meeting agendas, moving your own tasks, filing notes into the right folder.

  2. Put the list into the agent's instructions. Dots supports custom rules, and most agents accept standing instructions. Spell it out: "Never send email to anyone outside the company. Never change a due date or owner on someone else's task. Ask me first." Be aware of the limit here. OpenAI's own FAQ says custom rules can't override certain built-in behavior, so treat rules as instructions the agent should follow, and keep your real control in the permissions you grant.

  3. Remove the send permission where you can. If the agent is connected to your mail with full access, it can send mail when its rules allow it. If your use case is triage and drafts, connect it with the narrowest access available, or keep mail out of its connections until you trust its judgment.

  4. Match the review to the risk. Name who signs off at each level. A reminder to your own team can go out unreviewed. A draft to a client gets your eyes every time. Anything involving money, safety, compliance or a public statement gets a second person. Write the names down so "the agent said so" never becomes the explanation.

Issue 3: The agent's status report can be wrong with total confidence

The second Dots report, an agent claiming progress on work that had stopped, is the more dangerous failure for a PM. A human who is stuck usually sounds stuck. An agent that misreads a board will produce a clean, confident summary that is wrong.

The same pattern shows up in the UNSW piece as warning signs of deference to AI: decisions justified with "because the agent said so," fewer source checks, meetings that move faster with fewer questions, and override rates near zero on complex work. A near-zero override rate looks like accuracy. More often it means nobody is checking.

Options:

  1. Spot-check the status report against the board once a week. Pick three items the agent marked on track and open them. Check the last real update, the owner, and the date. If one of three is wrong, the whole report needs a closer look that week.

  2. Require evidence for each status line. Instruct the agent to cite the ticket, document or message behind every claim ("On track: last update 10/9 by owner, see ticket 214"). A status line with no source is a status line you can't trust.

  3. Treat "in progress" with no recent activity as stalled. Set a rule: any task the agent reports as active with no human update in five working days gets flagged as a possible stall, not counted as progress.

  4. Track your own override rate. Keep a rough count of how often you change or reject an agent's draft. If it drops to zero on complex work, assume you've stopped reading closely and do a full review.

Issue 4: The agent can't see the events you care about

The Dots review also points out a practical gap. Dots can be triggered by new Gmail messages, new Slack messages and GitHub pull request activity. It can't react to a Jira status change, a new Asana task or a missed due date. The workaround is a scheduled check, which means a delay between the event and the response.

That's fine for a morning digest. It's not fine if your team assumes the agent will catch a blocker the moment it appears.

Options:

  1. Tell the team what the agent watches and how often. "The agent checks the board at 8 a.m. and 2 p.m." sets the right expectation. Nobody should assume real-time coverage that doesn't exist.

  2. Keep urgent escalation human. Blockers, safety issues and client complaints should go to a person through your normal channel. Don't route them through a scheduled check.

  3. Use the right tool for event-driven rules. If you need "when status changes to Blocked, notify the lead," build it in the project tool's own automation, which reacts to board events directly.

Issue 5: The agent remembers things you can't see

According to the same review, you can't view or delete individual Dots memories, and disconnecting a plugin doesn't remove what the agent already learned. Deleting the agent is the only full reset. Other tools handle this differently, and this may change, but the pattern is common enough to plan around: what you connect an agent to today may stay in its memory after you disconnect it.

For PMs who handle client data, contracts or personnel matters, that's a data-handling question before it's a productivity question.

Options:

  1. Use a work account for work data. Don't connect a personal AI account to client or company systems. The review makes the same recommendation.

  2. Connect the minimum. Start with one board or one folder, not your whole drive. Add access when a specific task needs it.

  3. Check your company's AI policy before connecting anything. If there isn't one, ask. The ICO's call for evidence and Gartner's cancellation forecast both point the same way: organizations will tighten rules on agents over the next year, and it's easier to start inside those rules than to unwind a setup later.

A starting setup for this week

If you want to try an agent on a live project without creating a mess, this is a reasonable first configuration:

  1. Connect it to one project board, read-only.

  2. Have it draft a Monday status summary, with a source cited for each line.

  3. Spot-check three lines against the board every Monday for two weeks.

  4. Write your draft / advise / execute list and add it to the agent's instructions.

  5. After two clean weeks, allow it to execute the lowest-risk items on your list, such as internal reminders and agenda drafts. Leave client communication, dates, owners and costs in draft mode.

  6. Tag anything it changes so the project history stays readable.

None of this requires a policy committee. It's the same thing a good PM does with a new team member: a short probation period, a clear list of what they can decide on their own, and a weekly check that what they report matches what's on the board.

The agents will keep getting more capable. The question each PM has to answer is which decisions stay with a person, and that answer is much easier to write down now, before the first agent sends something you have to explain to a client.